![]()

Key Takeaways:
- The Gordie Howe delay prevented businesses from realizing anticipated savings from lower tolls, reduced congestion and shorter crossing times.
- The Sanity Project estimates that roughly five months of delay resulted in approximately $135 million to $155 million in direct economic costs.
- Canada-U.S. trade did not stop during the delay, but businesses continued relying on existing infrastructure while the new crossing remained unavailable.
- The approximately C$6.4-billion public infrastructure investment demonstrates why the economic value of major projects depends on timely access as well as successful construction.
- Infrastructure policy should consider the opportunity costs created when completed or nearly completed assets cannot deliver their intended economic benefits.
Infrastructure delays are often discussed in terms of construction schedules, political disagreements and opening dates. The more consequential question is what those delays cost the economy while a completed asset remains unavailable. The delayed opening of the Gordie Howe International Bridge between Windsor, Ontario, and Detroit, Michigan, provides a useful case study in that often-overlooked cost.
The bridge was originally expected to open in June 2026, but political disagreements between Canada and the United States delayed its opening until July 27. Reuters reported that the dispute centred partly on toll revenue and governance, with an agreement eventually allowing the bridge to proceed.
Expert analysis from The Sanity Project explains that, for Canada, the issue was not simply that a new bridge sat unused for several weeks. The country had already financed the construction of the major public infrastructure project, while businesses and commercial carriers continued relying on existing crossings. That creates an important distinction between the cost of building infrastructure and the economic value lost when completed infrastructure cannot yet be used.
What Was Lost During the Delay?
The Gordie Howe International Bridge was designed to provide a more direct and reliable connection between Ontario’s Highway 401 and Michigan’s Interstate 75. Its economic case has long rested on reducing crossing times, improving reliability and increasing capacity in one of North America’s most important trade corridors.
A major economic assessment commissioned by the Windsor-Detroit Bridge Authority estimated that trucks could save approximately 20 minutes per crossing compared with existing conditions. At roughly 2.5 million truck crossings annually, that amounted to almost 850,000 hours of aggregate time savings each year. The study estimated the present value of truck time savings at between $1.1 billion and $2.3 billion over the bridge’s service life. Those benefits could not be realized while the new crossing remained closed.
This missed economic opportunity and the approximately five-month delay represented roughly $135 million to $155 million in direct economic costs. The calculation illustrates how even a relatively short delay can become financially significant when applied to a major trade corridor with substantial commercial traffic.
The costs extend beyond a single line item. Businesses could not take advantage of anticipated lower tolls, shorter journeys and reduced congestion through the new crossing. Truck operators continued to incur the time and operating costs associated with existing infrastructure, while the economic benefits associated with the completed bridge remained unrealized.
Trade Did Not Stop — But That Does Not Mean There Was No Cost
One misconception surrounding infrastructure disputes is that failure to open a new international crossing would necessarily halt Canada-U.S. trade. That is not how the Windsor-Detroit corridor operates. Commercial traffic could continue using established crossings, particularly the Ambassador Bridge. The existence of alternative infrastructure meant that goods could still move between the two countries.
The economic question was therefore not whether trade would continue. It was how efficiently and affordably that trade could continue.
The existing corridor has handled enormous volumes of commercial traffic for years. The Detroit Regional Chamber reported that the Detroit-Windsor corridor handles more than four million truck crossings annually and nearly $70 billion in two-way trade.
A delayed alternative consequently meant continued dependence on infrastructure that the new project was specifically designed to supplement. The Gordie Howe bridge was intended to provide additional capacity and redundancy while improving the reliability of cross-border freight movement.
That distinction matters when evaluating infrastructure policy. An unused bridge does not necessarily produce an immediate economic shutdown, but it can prevent businesses from realizing the efficiency gains that justified the investment in the first place.
The Cost of Idle Public Infrastructure
The Gordie Howe project also raises a broader question about the economics of public infrastructure. Canada financed the approximately C$6.4 billion project, which includes the bridge, ports of entry and connecting infrastructure. The investment was made on the expectation that the completed crossing would generate economic benefits over decades.
Keeping such an asset unavailable does not erase those long-term benefits, but it postpones them. Businesses continue operating under existing constraints, while the public investment is not yet generating its intended transportation and economic advantages.
This is particularly important for infrastructure connected to supply chains. A delay affecting a local facility may inconvenience individual users. A delay affecting a major international trade corridor can impose costs across trucking, manufacturing, logistics and other industries that depend on predictable border movement.
The bridge’s economic rationale therefore extends beyond the structure itself. Earlier research concluded that improved crossing times and reliability could generate billions of dollars in economic savings over the bridge’s lifetime.
Infrastructure Decisions Have Opportunity Costs
The Gordie Howe experience demonstrates why infrastructure policy should consider opportunity costs alongside construction budgets.
The headline figure attached to a project typically describes what governments spend to build it. A fuller economic assessment also needs to consider what businesses, workers and consumers gain once the infrastructure becomes operational — and what they lose when political, regulatory or administrative decisions postpone those benefits.
The Sanity Project’s analysis places the Gordie Howe delay within that broader framework, treating the opening dispute as an economic question rather than simply a political controversy. The resulting calculation provides a useful reminder that delays can carry measurable costs even when the underlying trade relationship remains operational.
For governments planning major infrastructure, the lesson is straightforward: completing construction is only one stage of realizing an investment. The economic return begins when the asset can actually perform the function for which it was built.
In the case of the Gordie Howe International Bridge, the eventual opening restored access to the infrastructure’s intended benefits. The period before that opening, however, demonstrates that political and administrative delays can themselves become an economic liability.
The Sanity Project
bo.sanityproject@gmail.com
Winnipeg, Manitoba
Winnipeg
Manitoba
R3B
Canada